Question 378 - PRINCE2-7-Foundation discussion
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the 'quality management technique should this occur?
A.
Gathering user inputs
B.
Accepting products
C.
Describing the quality management approach
D.
controlling quality
Your answer: