Question 378 - PRINCE2-7-Foundation discussion

Report
Export

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the 'quality management technique should this occur?

A.
Gathering user inputs
Answers
A.
Gathering user inputs
B.
Accepting products
Answers
B.
Accepting products
C.
Describing the quality management approach
Answers
C.
Describing the quality management approach
D.
controlling quality
Answers
D.
controlling quality
Suggested answer: C