Question 389 - PRINCE2-7-Foundation discussion

Report
Export

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

A.
Managing product delivery
Answers
A.
Managing product delivery
B.
controlling a stage
Answers
B.
controlling a stage
C.
Managing a stage boundary
Answers
C.
Managing a stage boundary
D.
closing a project
Answers
D.
closing a project
Suggested answer: A

Explanation:

The 'Managing Product Delivery' process in PRINCE2 is where the specified quality methods are applied to ensure that a product meets its quality criteria. This process focuses on the acceptance, execution, and delivery of the project's products, ensuring that they are produced to the defined quality standards as part of the overall project delivery.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation