Question 403 - PRINCE2-7-Foundation discussion

Report
Export

What is a description of a leadership activity within a project?

A.
Understanding and working with different departments outside of the project team
Answers
A.
Understanding and working with different departments outside of the project team
B.
Agreeing a work package with a team manager to deliver products using specific tools
Answers
B.
Agreeing a work package with a team manager to deliver products using specific tools
C.
Ensuring that a co-located project team uses the agreed communication methods
Answers
C.
Ensuring that a co-located project team uses the agreed communication methods
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Answers
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Suggested answer: B

Explanation:

A leadership activity within a PRINCE2 project involves several responsibilities, one of which is agreeing on work packages with team managers. This agreement includes specifying the tools and techniques to be used for product delivery. This activity is crucial for ensuring clarity and mutual understanding of how work is to be conducted, facilitating effective delegation and accountability within the project team.

Reference: (PRINCE2 7 Foundation Study Guide, AXELOS)