How should effective issue management be applied When changing management products?

A.
By changing the issue management approach at the end of each stage to reflect lessons
Answers
A.
By changing the issue management approach at the end of each stage to reflect lessons
B.
By creating new versions of a management product when a change is approved
Answers
B.
By creating new versions of a management product when a change is approved
C.
By Implementing a change budget to fund changes to the project product
Answers
C.
By Implementing a change budget to fund changes to the project product
D.
By recording the required change to a management product as an off-specification
Answers
D.
By recording the required change to a management product as an off-specification
Suggested answer: B

Explanation:

Effective issue management in PRINCE2 should involve creating new versions of management products whenever a change is approved. This practice ensures that all documentation reflects the most current understanding and agreements regarding the project's scope and requirements. It helps maintain the integrity and relevance of the project documentation throughout its lifecycle, facilitating effective governance and control.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)