Which is an internal factor to consider when tailoring PRINCE??

A.
The safety legislation
Answers
A.
The safety legislation
B.
The environmental standards
Answers
B.
The environmental standards
C.
The industry's regulations
Answers
C.
The industry's regulations
D.
The organization's procedures
Answers
D.
The organization's procedures
Suggested answer: D

Explanation:

An internal factor to consider when tailoring PRINCE2 to a specific project environment is 'The organization's procedures.' Tailoring must take into account internal practices, procedures, and organizational culture to ensure that the project management approach aligns well with internal governance and can be effectively integrated within the organizational context.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)