Question 452 - PRINCE2-7-Foundation discussion

Report
Export

The project manager needs to confirm that operational teams are responsible for the running of the outputs.

During which step of the 'organizational design and development' technique should the project manager ensure this?

A.
Manage the ongoing changes to the project ecosystem
Answers
A.
Manage the ongoing changes to the project ecosystem
B.
Transition the project into the organizational ecosystem
Answers
B.
Transition the project into the organizational ecosystem
C.
Understand the organizational ecosystem
Answers
C.
Understand the organizational ecosystem
D.
Develop the project ecosystem
Answers
D.
Develop the project ecosystem
Suggested answer: B

Explanation:

The project manager needs to ensure that operational teams are responsible for running the project outputs during the step 'Transition the project into the organizational ecosystem'. This step involves integrating the project outcomes into the regular functions of the organization, ensuring that operational teams are prepared and accountable for maintaining and managing the project's outputs post-project completion.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)