Question 462 - PRINCE2-7-Foundation discussion

Report
Export

Thea project manager needs to report to the project board on the status of the project's issues.

Which management product should the project manager review?

A.
Project log
Answers
A.
Project log
B.
Project brief
Answers
B.
Project brief
C.
Checkpoint report
Answers
C.
Checkpoint report
D.
Highlight report
Answers
D.
Highlight report
Suggested answer: D

Explanation:

The Project Manager should review the Highlight Report to report to the Project Board on the status of the project's issues. The Highlight Report provides a regular summary of the stage status, including progress against the plan and details about any issues or risks, making it the appropriate management product for communicating current issues to the Project Board.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)