Question 462 - PRINCE2-7-Foundation discussion
Thea project manager needs to report to the project board on the status of the project's issues.
Which management product should the project manager review?
A.
Project log
B.
Project brief
C.
Checkpoint report
D.
Highlight report
Your answer: