You are implementing the Design Document for a large Enterprise Revenue Cloudprojecthaving multiple lookup price rules supporting a complex pricing requirement in the Buildphase. During construction the customer discovers additional logic and external datastores that need to be incorporated in order to achieve the correct pricing in a particular setof use cases. You estimate the lookup price rules will need to be modified, additional ruleswill need to be created and API development will beneeded. As an Implementationconsultant what is the appropriate course of action that should take in this predicament?
A.
Communication to the customer ongoing adjustment can be made as long as we're inthe build phase.
B.
Implement the lookup price rules immediately then review with the solution Architect.
C.
Communicate these changes to the project manager who will evaluate the impact toscope, timeline and budget them determine the next course of action
D.
Consult with the solution Architect first who will expedite the updates to the designdocuments, then implement the changes immediately.
E.
Gather more details, if it requires a low level of effort then implement immediatelybefore starting the next sprint, Otherwise Complete on the subsequent sprint.