Who can cancel a Sprint?

(choose the best answer)

A.
The Scrum Master
Answers
A.
The Scrum Master
B.
The Scrum Team.
Answers
B.
The Scrum Team.
C.
The Stakeholders.
Answers
C.
The Stakeholders.
D.
The Product Owner.
Answers
D.
The Product Owner.
Suggested answer: D

Explanation:

According to the Scrum Guide, the Product Owner can cancel a Sprint, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the Product Owner.