Question 227 - PSM I discussion

Report
Export

When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint? (choose the best answer)

A.
Yes, but only for Scrum Teams whose work has dependencies.
Answers
A.
Yes, but only for Scrum Teams whose work has dependencies.
B.
No, that is tar too nard and must be done in a hardening Sprint
Answers
B.
No, that is tar too nard and must be done in a hardening Sprint
C.
No, each Scrum Team stands alone.
Answers
C.
No, each Scrum Team stands alone.
D.
Yes, in order to accurately inspect what is done.
Answers
D.
Yes, in order to accurately inspect what is done.
Suggested answer: D

Explanation:

According to the Scrum Guide, when multiple Scrum Teams are working on the same product, they should integrate their Increments every Sprint, in order to accurately inspect what is done and ensure that there is no technical debt or unfinished work at the end of each Sprint. The other options are not valid, as they imply that integration can be skipped, delayed, or done only for some teams, which is not consistent with Scrum values and principles.