Which statement best describes the Sprint Backlog as the output ot the Sprint Planning?

(choose the best answer)

A.
Every item nas a designated owner.
Answers
A.
Every item nas a designated owner.
B.
It is ordered by the Product Owner.
Answers
B.
It is ordered by the Product Owner.
C.
Each task is estimated in hours.
Answers
C.
Each task is estimated in hours.
D.
It is the Developers plan for the Sprint
Answers
D.
It is the Developers plan for the Sprint
E.
It is a complete list of all work to be done in a Sprint.
Answers
E.
It is a complete list of all work to be done in a Sprint.
Suggested answer: D

Explanation:

According to the Scrum Guide, the Sprint Backlog is the Developers' plan for the Sprint, as it contains all the Product Backlog items selected for the Sprint and a plan for delivering them. The other options are not valid descriptions of the Sprint Backlog, as they are either incorrect (such as having a designated owner, being ordered by the Product Owner, or being a complete list of all work) or unnecessary (such as estimating each task in hours).