True or False: When scaling Scrum it is important to have multiple Scrum Teams working from one Product Backlog

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: A

Explanation:

When scaling Scrum, it is important to have multiple Scrum Teams working from one Product Backlog, because this ensures that they are aligned on the same product vision, goal, and value12.Having one Product Backlog also helps to reduce duplication, inconsistency, and waste, and to optimize the flow of work and feedback12.The Product Owner is accountable for managing the Product Backlog and ensuring that it is transparent, ordered, and refined for the multiple Scrum Teams3.The Scrum Teams collaborate with the Product Owner and each other to deliver a single integrated product Increment every Sprint3.

asked 23/09/2024
Rakesh Sonawane
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first