The only person who can abnormally terminate a Sprint is?

(choose the best answer)

A.
The Developers.
Answers
A.
The Developers.
B.
The Scrum Master.
Answers
B.
The Scrum Master.
C.
The Product Owner.
Answers
C.
The Product Owner.
D.
The Stakeholders.
Answers
D.
The Stakeholders.
Suggested answer: C

Explanation:

The Scrum Guide specifies that only the Product Owner has the authority to cancel a Sprint.This is because the Product Owner is responsible for maximizing the value of the product and may decide to cancel a Sprint if the Sprint Goal becomes obsolete or if they foresee that the current direction will not lead to a valuable outcome