Which of the following might be considered when ordering Product Backlog items?
(choose all that apply)
A.
Dependencies to other products.
B.
Value of Product Backlog items.
C.
Dependencies between Product Backlog items.
D.
Cost of delay.
E.
Cost of implementation.