What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the next Sprint's Sprint Planning?

(choose the best answer)

A.
Working with the Quality Assurance departments on the Increment of the current Sprint.
Answers
A.
Working with the Quality Assurance departments on the Increment of the current Sprint.
B.
There are no such activities. The next Sprint starts immediately after the current Sprint.
Answers
B.
There are no such activities. The next Sprint starts immediately after the current Sprint.
C.
Updating the project plan with the stakeholders.
Answers
C.
Updating the project plan with the stakeholders.
D.
Refining the Product Backlog.
Answers
D.
Refining the Product Backlog.
Suggested answer: D