When one speaks of 20% of something contributing 80% of the affect they are referring to what is known as the _________________.

A.
Shewhart Example
A.
Shewhart Example
Answers
B.
Pareto Principle
B.
Pareto Principle
Answers
C.
Balance Equation
C.
Balance Equation
Answers
D.
Connection Principle
D.
Connection Principle
Answers
Suggested answer: B

Using this data calculate the percentage of DPU.

A.
2.74
A.
2.74
Answers
B.
3.23
B.
3.23
Answers
C.
4.56
C.
4.56
Answers
D.
5.93
D.
5.93
Answers
Suggested answer: B

As a means of measuring the effects on other areas of a process as a result of changes in the primary metric we also define and track ________________.

A.
Parallel process metrics
A.
Parallel process metrics
Answers
B.
Secondary metrics
B.
Secondary metrics
Answers
C.
Tertiary metrics
C.
Tertiary metrics
Answers
D.
Industry standards
D.
Industry standards
Answers
Suggested answer: B

Calculate the Rolled Throughput Yield of this process using this data. Data. unit input: 1450, unit output: 1390, defects repaireD. 320, scrap: 60

A.
71.33%
A.
71.33%
Answers
B.
72.66%
B.
72.66%
Answers
C.
73.79%
C.
73.79%
Answers
D.
77.93%
D.
77.93%
Answers
Suggested answer: C

''A calculated time frame that matches customer demand'' is a definition of what Lean Principles term?

A.
Value Stream
A.
Value Stream
Answers
B.
Kaizen event
B.
Kaizen event
Answers
C.
Takt time
C.
Takt time
Answers
D.
Kanban
D.
Kanban
Answers
Suggested answer: C

What dollar amount of savings would a project show if it reduced your outstanding Accounts Receivable by $1.4 million dollars to $5.3 million total and your organization's marginal cost of capital was 6.2%?

A.
$43,400
A.
$43,400
Answers
B.
$86,800
B.
$86,800
Answers
C.
$117,500
C.
$117,500
Answers
D.
$328,600
D.
$328,600
Answers
Suggested answer: B

Which Element of Waste best describes 'the unnecessary movement of materials and goods'?

A.
Overprocessing
A.
Overprocessing
Answers
B.
Inventory
B.
Inventory
Answers
C.
Motion
C.
Motion
Answers
D.
Conveyance
D.
Conveyance
Answers
Suggested answer: D

A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker repair times by eliminating one of seven major elements of waste which is the Waste of __________.

A.
Motion
A.
Motion
Answers
B.
Conveyance
B.
Conveyance
Answers
C.
Inventory
C.
Inventory
Answers
D.
Waiting
D.
Waiting
Answers
Suggested answer: A

The Japanese born function of a Kanban event utilizes a specific, step-by-step approach meant to bring about major changes to a process.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

The primary objective in removal of waste is to improve the Order Production Cycle where the time from _________________ to the time of receipt of payment is compressed.

A.
Shift start
A.
Shift start
Answers
B.
Product development
B.
Product development
Answers
C.
Receipt of an order
C.
Receipt of an order
Answers
D.
New fiscal year
D.
New fiscal year
Answers
Suggested answer: C
Total 369 questions