Question 71

Report Export Collapse

HOTSPOT

A company uses a make-to-stock strategy for their key production components.

The number of active Kanbans for these components must be constant.

You need to configure a new Kanban rule.

How should you set up the Kanban type and replenishment strategy? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.


Become a Premium Member for full access
  Unlock Premium Member

Question 72

Report Export Collapse

HOTSPOT

A company produces homeopathic lotions for pain relief and uses Dynamics 365 for Finance and Operations.

Several components used in the production of the pain-relieving lotion and oils have special government-mandated reporting requirements.

You need to ensure the company can provide the appropriate reporting and tracking for these components.

Which parameters should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.


Become a Premium Member for full access
  Unlock Premium Member

Question 73

Report Export Collapse

DRAG DROP

A process manufacturing company is implementing Dynamics 365 for Finance and Operations. The company will use multiple process manufacturing functionalities including by-products.

You need to configure by-product formula allocation methods.

Which methods should you use? To answer, drag the appropriate by-product burden allocation methods to the correct scenarios. Each method may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.


Become a Premium Member for full access
  Unlock Premium Member

Question 74

Report Export Collapse

DRAG DROP

A company uses Dynamics 365 Process manufacturing.

Employees work a half day so that they can attend a company event. You have a rush order that must be completed that same day.

After reviewing the net requirements of the batch order, only 400 of the total quantity of 1400 units must be completed today. The production manager must retain the original batch number as the quantity of 400. The original batch number must appear on documentation for the customer.

You need to split the batch order onto two orders.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


Become a Premium Member for full access
  Unlock Premium Member

Question 75

Report Export Collapse

DRAG DROP

You are the product manager at an orange juice manufacturing company.

For every 1,000 pounds of orange juice, 20 pounds of orange pulp is created which can be sold or reused profitably. The cost is calculated as a weighted average between the quantity of orange juice that is reported as finished and the orange pulp based on the standard cost of each item.

You need to create the formula for orange juice that will produce orange pulp as a result of finishing a batch order.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


Become a Premium Member for full access
  Unlock Premium Member

Question 76

Report Export Collapse

DRAG DROP

A process manufacturing company is implementing rebates in Dynamics 365 for Finance and Operations for some of their customers on specific items.

You are the production consultant in charge of implementing the processes needed for calculating and applying the rebates for the subset of customer and items.

You need to implement the order of transactions to process the rebates.

In which order should the actions be performed? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.


Become a Premium Member for full access
  Unlock Premium Member

Question 77

Report Export Collapse

You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished.

You need to ensure that the values of attributes are updated and tracked.

What three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Become a Premium Member for full access
  Unlock Premium Member

Question 78

Report Export Collapse

A manufacturer produces HDMI cables. Typically, the item is manufactured.

The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member

Question 79

Report Export Collapse

A company produces paints and assembles bicycle frames.

You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.

Which two options can you use? Each correct answer presents part of solution.

NOTE: Each correct selection is worth one point.

Become a Premium Member for full access
  Unlock Premium Member

Question 80

Report Export Collapse

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.

A machine in the facility is defective and must be closed for repairs for the next two days.

You need to configure the resource calendar to close the resource for production for the next two days.

What should you do?

Become a Premium Member for full access
  Unlock Premium Member