If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team? (Choose the best answer.)

A.
Its productivity is likely to decrease.
A.
Its productivity is likely to decrease.
Answers
B.
Its productivity is likely to stay the same.
B.
Its productivity is likely to stay the same.
Answers
C.
Its productivity is likely to increase.
C.
Its productivity is likely to increase.
Answers
D.
We do not know until a Sprint has run
D.
We do not know until a Sprint has run
Answers
Suggested answer: A

A Scrum Master is introducing Scrum to a new Development Team. The Development Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take? (Choose the best answer.)

A.
Call a meeting between the Development Team and senior management.
A.
Call a meeting between the Development Team and senior management.
Answers
B.
Comply with the decision of the self-organizing team.
B.
Comply with the decision of the self-organizing team.
Answers
C.
Consult with the Product Owner to see how he/she feels about the situation.
C.
Consult with the Product Owner to see how he/she feels about the situation.
Answers
D.
Begin facilitating productive and useful Sprint Retrospectives.
D.
Begin facilitating productive and useful Sprint Retrospectives.
Answers
Suggested answer: D

Which of the following are true about the Product Owner role? (Choose the best two answers.)

A.
The Product Owner is one person.
A.
The Product Owner is one person.
Answers
B.
The Product Owner is accountable for ordering the Product Backlog.
B.
The Product Owner is accountable for ordering the Product Backlog.
Answers
C.
Multiple people can share the Product Owner role on a Scrum Team.
C.
Multiple people can share the Product Owner role on a Scrum Team.
Answers
D.
The Product Owner role can be played by a committee or a team of people.
D.
The Product Owner role can be played by a committee or a team of people.
Answers
Suggested answer: A, B

True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

When does the second Sprint start? (Choose the best answer.)

A.
Once the architectural changes for the second Sprint have been approved by the senior architect.
A.
Once the architectural changes for the second Sprint have been approved by the senior architect.
Answers
B.
After the Product Backlog for the second Sprint has been selected.
B.
After the Product Backlog for the second Sprint has been selected.
Answers
C.
Immediately after the first Sprint.
C.
Immediately after the first Sprint.
Answers
D.
After the customer completes acceptance testing of the first Sprint.
D.
After the customer completes acceptance testing of the first Sprint.
Answers
Suggested answer: C

What is included in the Sprint Backlog? (Choose the best answer.)

A.
User Stories.
A.
User Stories.
Answers
B.
Tasks.
B.
Tasks.
Answers
C.
Use Cases.
C.
Use Cases.
Answers
D.
Tests.
D.
Tests.
Answers
E.
Any of the above (or others) which are a decomposition of the selected Product Backlog items.
E.
Any of the above (or others) which are a decomposition of the selected Product Backlog items.
Answers
Suggested answer: E

What enhances the transparency of an increment? (Choose the best answer.)

A.
Doing all work needed to meet the definition of "Done"
A.
Doing all work needed to meet the definition of "Done"
Answers
B.
Reporting Sprint progress to the stakeholders daily
B.
Reporting Sprint progress to the stakeholders daily
Answers
C.
Keeping track of and estimating all undone work to be completed in a separate Sprint.
C.
Keeping track of and estimating all undone work to be completed in a separate Sprint.
Answers
D.
Updating Sprint tasks properly in the electronic tracking tool.
D.
Updating Sprint tasks properly in the electronic tracking tool.
Answers
Suggested answer: A

Who determines how work is performed during the Sprint? (Choose the best answer.)

A.
Architects.
A.
Architects.
Answers
B.
The Development Team.
B.
The Development Team.
Answers
C.
The Scrum Master.
C.
The Scrum Master.
Answers
D.
Subject matter experts.
D.
Subject matter experts.
Answers
E.
Development Team managers.
E.
Development Team managers.
Answers
Suggested answer: B

Why should the Product Owner be present at the Daily Scrum? (Choose the best answer.)

A.
He/She doesn't need to be there.
A.
He/She doesn't need to be there.
Answers
B.
To hear about impediments in functionality.
B.
To hear about impediments in functionality.
Answers
C.
To represent the stakeholder's point of view.
C.
To represent the stakeholder's point of view.
Answers
D.
To participate as a Scrum Team member.
D.
To participate as a Scrum Team member.
Answers
Suggested answer: A

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply?

(Choose the best two answers.)

A.
Involve the complete Development Team.
A.
Involve the complete Development Team.
Answers
B.
Use coaching techniques; such as open questions and active listening.
B.
Use coaching techniques; such as open questions and active listening.
Answers
C.
Ask an external technical specialist to make the decision.
C.
Ask an external technical specialist to make the decision.
Answers
D.
Send every team member to the company's Human Resources department to express their concerns.
D.
Send every team member to the company's Human Resources department to express their concerns.
Answers
Suggested answer: A, B