Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

A.

Update the issue log.

Answers
A.

Update the issue log.

B.

Apply the contingency plan.

Answers
B.

Apply the contingency plan.

C.

Transfer the risk.

Answers
C.

Transfer the risk.

D.

Submit a change request.

Answers
D.

Submit a change request.

Suggested answer: B

Explanation:

Applying the contingency plan is the immediate response to mitigate a security risk. CompTIA Project+ emphasizes the importance of having pre-established contingency plans to handle potential risks promptly and effectively.