As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
A.
Executing the approved contingency plan
B.
Constructing an Ishikawa diagram to determine the root cause
C.
Using a Pareto chart to prioritize the different causes
D.
Engaging the senior management team in regard to the issue