As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

A.

Executing the approved contingency plan

Answers
A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

Answers
B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

Answers
C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Answers
D.

Engaging the senior management team in regard to the issue

Suggested answer: B

Explanation:

An Ishikawa diagram, also known as a fishbone diagram, is a tool used to identify and analyze the root causes of a particular problem. CompTIA Project+ references this tool as essential for quality management and problem-solving.