Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

A.
Evaluating the project
Answers
A.
Evaluating the project
B.
Releasing the resources
Answers
B.
Releasing the resources
C.
Closing the contracts
Answers
C.
Closing the contracts
D.
Reconciling the budget
Answers
D.
Reconciling the budget
Suggested answer: A

Explanation:

Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements. Reference: CompTIA Project+ Study Guide Section 4.4.4