By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

A.
Allocate resources.
Answers
A.
Allocate resources.
B.
Determine the project budget
Answers
B.
Determine the project budget
C.
Develop a communication plan.
Answers
C.
Develop a communication plan.
D.
Establish baselines.
Answers
D.
Establish baselines.
Suggested answer: D

Explanation:

The next step after defining tasks, durations, resources, and costs is to establish baselines. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Establishing baselines involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution34