Question 221 - PK0-005 discussion
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
A.
Business requirement
B.
Client statement of work
C.
Formal contract
D.
Project charter