During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A.
Ishikawa diagram
Answers
A.
Ishikawa diagram
B.
Scatter diagram
Answers
B.
Scatter diagram
C.
Pareto chart
Answers
C.
Pareto chart
D.
Decision tree
Answers
D.
Decision tree
Suggested answer: C

Explanation:

The Pareto chart should be used to identify the most important causes of issues during a quality analysis review. The Pareto chart is a graphical representation of the frequency and impact of different causes, helping to identify the most common and impactful causes. Reference: CompTIA

Project+ Study Guide Section 3.3.3