A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

A.
Milestone chart
Answers
A.
Milestone chart
B.
Gantt chart
Answers
B.
Gantt chart
C.
PERT chart
Answers
C.
PERT chart
D.
WBS
Answers
D.
WBS
Suggested answer: B

Explanation:

A gantt chart is a visual representation of a project timeline that shows the tasks, durations, dependencies, and resources of a project in a horizontal bar chart format. A gantt chart can help a project manager to plan, monitor, and control the project progress, scope, and quality. A gantt chart is different from a milestone chart, which only shows the key events or deliverables of a project without the details of the tasks. A gantt chart is also different from a PERT chart, which is a network diagram that shows the logical relationships and sequence of tasks in a project. A gantt chart is also different from a WBS, which is a hierarchical breakdown of the project scope into smaller and manageable components. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Schedule Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 6: Schedule Management2; What Is a Gantt Chart? 7 Examples for Project Management3; 3 types of visual project management: Timelines, calendars, and boards (with examples)4