Which of the following should a project manager consult when deciding how to send updates regarding deliverables?

A.

Dashboard

Answers
A.

Dashboard

B.

Status report

Answers
B.

Status report

C.

Meeting minutes

Answers
C.

Meeting minutes

D.

Communication plan

Answers
D.

Communication plan

Suggested answer: D

Explanation:

A communication plan details the communication requirements, including methods, frequency, and stakeholders for each type of update. According to CompTIA Project+, this plan is essential for ensuring effective and organized communication throughout the project.