Question 187 - PgMP discussion
You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?
A.
Stakeholder communication information
B.
Schedule variances
C.
Program schedule updates
D.
Change requests