List of questions
Related questions
Question 188 - PgMP discussion
Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?
A.
Alternative identification
B.
Work packages
C.
Requirements
D.
Scope decomposition
Your answer:
0 comments
Sorted by
Leave a comment first