Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

A.
Work breakdown structure
Answers
A.
Work breakdown structure
B.
Program network diagram
Answers
B.
Program network diagram
C.
Program scope baseline
Answers
C.
Program scope baseline
D.
Activity list
Answers
D.
Activity list
Suggested answer: A