Question 193 - PgMP discussion
You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?
A.
Change requests
B.
Performance reports
C.
Forecasts
D.
Earned value management