Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?
A.
Close the constituent projects before closing the program
B.
Complete the program's budget
C.
Release the program's resources
D.
Sign the certificate of program closure