Question 199 - PgMP discussion
Rick is a Program Manager for a large construction program. The program contains four projects. Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?
A.
Project charter
B.
Program scope statement
C.
Program performance report
D.
Program charter