Rick is a Program Manager for a large construction program. The program contains four projects. Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?

A.
Project charter
Answers
A.
Project charter
B.
Program scope statement
Answers
B.
Program scope statement
C.
Program performance report
Answers
C.
Program performance report
D.
Program charter
Answers
D.
Program charter
Suggested answer: B