Question 200 - PgMP discussion

Report
Export

Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?

A.
Lessons learned
Answers
A.
Lessons learned
B.
Supporting details
Answers
B.
Supporting details
C.
Program management plan updates
Answers
C.
Program management plan updates
D.
Assumptions
Answers
D.
Assumptions
Suggested answer: A