Question 201 - PgMP discussion
You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.
In which of the following processes are you working on?
A.
Plan Communication
B.
Distribute Information
C.
Report Program Performance
D.
Monitor and Control Program Performance
Your answer: