Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution.

Choose all that apply.

A.
Inspection and audits
Answers
A.
Inspection and audits
B.
Budget management system
Answers
B.
Budget management system
C.
Supplier performance review
Answers
C.
Supplier performance review
D.
Contract performance review
Answers
D.
Contract performance review
Suggested answer: A, B, D