You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?
A.
Report Program Performance
B.
Monitor and Control Program Scope
C.
Monitor and Control Program Schedule
D.
Monitor and Control Program Performance