Question 216 - PgMP discussion

Report
Export

You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

A.
Audit reports
Answers
A.
Audit reports
B.
Program management plan
Answers
B.
Program management plan
C.
Program performance reports
Answers
C.
Program performance reports
D.
Program issues register updates
Answers
D.
Program issues register updates
Suggested answer: D