You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request.
Which of the following is true regarding this scenario?
A.
The new Program Master Schedule is created containing the approved changes.
B.
Separate project is made to ensure that the approved changes are included in the program.
C.
Project charter is upgraded to include the approved changes in the program.
D.
The Program Master Schedule is updated to reflect the changes.