All of the following are benefits of a program except for which one?

A.
Projects can operate independently of one another.
Answers
A.
Projects can operate independently of one another.
B.
Resource management in a program allows resources to be shared across all projects in the program.
Answers
B.
Resource management in a program allows resources to be shared across all projects in the program.
C.
The program manager can use the same approach in stakeholder management for all projects in the program.
Answers
C.
The program manager can use the same approach in stakeholder management for all projects in the program.
D.
All projects follow the policies of the program and organization.
Answers
D.
All projects follow the policies of the program and organization.
Suggested answer: A