Question 221 - PgMP discussion
Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?
A.
Change request log
B.
Approved change requests
C.
Change requests
D.
Program management plan