Which of the following statements are true regarding program scope changes? (Choose three.)

A.
Scope changes may originate from the stake holders.
Answers
A.
Scope changes may originate from the stake holders.
B.
Change requests for a particular project have to be approved by the project manager irrespective of their potential impact on multiple projects.
Answers
B.
Change requests for a particular project have to be approved by the project manager irrespective of their potential impact on multiple projects.
C.
The program has a change control board that analyzes changes at the program level.
Answers
C.
The program has a change control board that analyzes changes at the program level.
D.
The change control process on a program is often hierarchical.
Answers
D.
The change control process on a program is often hierarchical.
Suggested answer: A, C, D