ExamGecko
Home Home / PMI / PgMP
Question list
Search
Search

List of questions

Search

Related questions











Question 234 - PgMP discussion

Report
Export

You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program.

They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

A.
Avoidance
Answers
A.
Avoidance
B.
Mitigation
Answers
B.
Mitigation
C.
Transference
Answers
C.
Transference
D.
Workaround
Answers
D.
Workaround
Suggested answer: B
asked 23/09/2024
law ryan
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first