Communication is large percentage of program execution as the program manager must communicate with the appropriate stakeholders. In larger programs face-to-face communication is not always possible. When emails are used what verbal aspect of communication is lost?

A.
Barriers
Answers
A.
Barriers
B.
Noise
Answers
B.
Noise
C.
Nonverbal
Answers
C.
Nonverbal
D.
Paralingual
Answers
D.
Paralingual
Suggested answer: D