Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

A.
Risk avoidance
Answers
A.
Risk avoidance
B.
Risk transference
Answers
B.
Risk transference
C.
Risk mitigation
Answers
C.
Risk mitigation
D.
Risk acceptance
Answers
D.
Risk acceptance
Suggested answer: C