Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

A.
Fallback plan
Answers
A.
Fallback plan
B.
Risk response plan
Answers
B.
Risk response plan
C.
Mitigation management plan
Answers
C.
Mitigation management plan
D.
Mitigation plan
Answers
D.
Mitigation plan
Suggested answer: A