Question 293 - PgMP discussion
An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved, but the stakeholders are concerned that the delivery method of the program may not meet their expectations.
Using the program master schedule, what will the program manager incorporate to align the program with the expectations of the stakeholders?
A.
Program work breakdown structure (PWBS), program scope statement, and benefits management plan
B.
PWBS, benefits management plan, and program financial management plan
C.
Program charter, PWBS, and program scope statement
D.
Program scope statement, benefits management plan, and program financial management plan