A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?
A.
Key performance indicators
B.
Benefits management plan
C.
Communications management plan
D.
Ishikawa diagram