A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.

What tool should be used to trigger a planned response when receiving lower than expected results?

A.
Key performance indicators
Answers
A.
Key performance indicators
B.
Benefits management plan
Answers
B.
Benefits management plan
C.
Communications management plan
Answers
C.
Communications management plan
D.
Ishikawa diagram
Answers
D.
Ishikawa diagram
Suggested answer: A