The program manager defines the program objectives, requirements, and develops a high-level road map. To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?

A.
Program governance board
Answers
A.
Program governance board
B.
Program management office
Answers
B.
Program management office
C.
Change control board
Answers
C.
Change control board
D.
Project managers on the program
Answers
D.
Project managers on the program
Suggested answer: A