An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.

What should the team do?

A.
Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.
Answers
A.
Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.
B.
Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.
Answers
B.
Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.
C.
Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.
Answers
C.
Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.
D.
Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.
Answers
D.
Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.
Suggested answer: A