How should a project leader manage stakeholder expectations in an agile project?

A.
Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.
Answers
A.
Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.
B.
Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.
Answers
B.
Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.
C.
Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.
Answers
C.
Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.
D.
Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.
Answers
D.
Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.
Suggested answer: A